Provision was therefore made in the Harbour of Refuge
Ordinance (Section 4 sub-section (4)) for its execution.
Section 12 of the Ordinance makes provision for the award
of compensation to owners whose property may be prejudicial-
-ly affected by the proposed works.
(1). Shaukiwan Waterworks Extension, $40,000 .
Owing principally to the opening of the Taikoo Shipyard,
there has been a great development in this neighbourhood
which renders works for increasing the water supply to the
district a matter of urgent necessity. The fact that the
most suitable sites in the locality for reservoirs have
been disposed of in the past to the Taikoo Sugar Refinery
has rendered the provision of a scheme on economical lines
a difficult matter. A more detailed account of the scheme
will be forwarded to Your Lordship in due course.
(m). Additional Service Reservoir, West
Point, $30,000.
In consequence of the necessity of
conserving the contents of the Pokfulam Reservoir for the
supply of the Hill District and High Levels of the City,
it is necessary to distribute water from the Tytam Reser-
-voirs over a large portion of the Western District of the
City. Owing to the great variation in level of the
district to he served, the pressure obtainable in the
upper